Cygnus Rendezvous and Capture: This morning the crew monitored the Cygnus approach from the Cupola Robotic Workstation and successfully captured Cygnus using the Space Station Remote Manipulator System (SSRMS) at 6:28 am CDT. The Ground Robotics team maneuvered Cygnus into position to inspect the Passive Common Berthing Mechanism (CBM), and berthed Cygnus onto the Node-1 Nadir Active CBM. Later, the crew removed the Centerline Berthing Camera System (CBCS) from the Node-1 Nadir hatch window. The crew performed a leak check and configured the vestibule for ingress. Controller Panel Assembly (CPA) removal and hatch opening/ingress are scheduled for Thursday, October 27th. Crew Quarters (CQ) 9 Volt Battery Changeout: Today, the crew replaced the 9 volt batteries in all four CQs. This maintenance is required every twelve months. These batteries are used to power the Caution & Warning (C&W) alarm speakers and the Egress Light Emitting Diodes (LEDs). Today’s Planned Activities All activities were completed unless otherwise noted. USOS Window Shutter Close HRF Generic Urine Collection HRF Generic Sample MELFI Retrieval Insertion Operations CONJUGATION ТБУ-[В]#02 Thermostat Setup KORREKTSIA. Taking food and liquids (medicine) registration in flight log Centerline Berthing Camera System (CBCS) Powerup Closing Window Shutters # 6, 8, 9, 12, 13, 14 T2 Crew Handover ISS Crew Adaptation Photo/TV Ghost Camera in Cuopla on SSC power recording ISS HAM Video Power Down Robotics Workstation (RWS) Configuration Cygnus PCS Command and PROX Link Verification HRF Generic Sample MELFI Insertion Operations Robotic Workstation (RWS) High Definition (HD) Monitor Downlink Cygnus R-BAR Approach Space Station Remote Manipulator System (SSRMS) Cygnus Capture Video Recording of greetings Remote Workstation Monitor HD Video Downlink Deactivation RWS. HRF Generic Urine Collection Stow BIOPLENKA. Cryogem-03 thermostat setup Regenerative Environmental Control and Life Support System (RGN) WSTA Fill KORREKTSIA. Taking food and liquids (medicine) registration in flight log СОЖ maintenance In Flight Maintenance (IFM) Crew Quarters (CQ) Battery Remove and Replace PCS Laptop Relocate Symbolic Activity PCS Laptop Relocate Node 1 Centerline Berthing Camera System (CBCS) Removal Ghost camera teardown in Cupola Robotic Workstation (RWS) Teardown Symbolic Cygnus/Node 1 Pressurization and Leak Check Node 1 Nadir to Cygnus Vestibule Outfitting Vacuum cleaning behind panels 405 and 406 in MRM 1 MICROVIR. Glovebox-S hardware setup ISS HAM Video Power Up Meteor Shutter Open Space Headaches – Daily Questionnaire Cygnus PROX Switch OFF Completed Task List Items None Ground Activities All activities were completed unless otherwise noted. SSRMS Maneuver to N1 Nadir CBM CBM Bolting Operations Three-Day Look Ahead: Monday, 10/24: BEAM Ingress, Airway Monitoring Setup, Cygnus Cargo Transfer Review Tuesday, 10/25: Emer H/W Fam, Veggie-3, Airway Monitoring Wednesday, 10/26: Soyuz Drill, Neuromapping, Dosetrack, Meteor, JAXA EPO QUICK ISS Status – Environmental Control Group: Component Status Elektron On Vozdukh Manual [СКВ] 1 – SM Air Conditioner System (“SKV1”) On [СКВ] 2 – SM Air Conditioner System (“SKV2”) Off Carbon Dioxide Removal Assembly (CDRA) Lab Standby Carbon Dioxide Removal Assembly (CDRA) Node 3 Operate Major Constituent Analyzer (MCA) Lab Operate Major Constituent Analyzer (MCA) Node 3 Idle Oxygen Generation Assembly (OGA) Process Urine Processing Assembly (UPA) Process Trace Contaminant Control System (TCCS) Lab Off Trace Contaminant Control System (TCCS) Node 3 Full Up
October 24, 2016 at 12:00AM
from NASA http://ift.tt/2dCqIP0
via IFTTT
沒有留言:
張貼留言