2017年12月6日 星期三

Hearing on NASA Space Telescopes

NASA: Preliminary Observations on the Management of Space Telescopes, Cristina Chaplain GAO

"GAO's ongoing work indicates that these projects are each making progress in line with their phase of the acquisition cycle but also face some challenges. For example, the current launch date for the James Webb Space Telescope (JWST) project reflects a 57-60-month delay from the project's original schedule. GAO's preliminary observations indicate this project still has significant integration and testing to complete, with very little schedule reserve remaining to account for delays. Therefore, additional delays beyond the delay of up to 8 months recently announced are likely, and funding available under the $8 billion Congressional cost cap for formulation and development may be inadequate."

- Hearing charter

- Prepared statements: Thomas Zurbuchen, Thomas Young, Matt Mountain, Chris McKee



from NASA Watch http://ift.tt/2iytXXT