GAO On Artemis: Behind Schedule, Over Cost, Lacking Clear Direction

GAO: NASA Human Space Exploration - Significant Investments in Future Capabilities Require Strengthened Management Oversight

"What GAO Found

The National Aeronautics and Space Administration (NASA) again delayed the planned launch date for Artemis I, the first uncrewed test flight involving three closely related human spaceflight programs--the Orion crew vehicle, Space Launch System (SLS), and Exploration Ground Systems (EGS). Together, these programs aim to continue human space exploration beyond low-Earth orbit. The most recent delay, to November 2021, resulted in part from manufacturing challenges and represents a 36-month slip since NASA established a schedule to measure performance in 2014. This new launch date does not account for the effects of COVID-19. According to NASA officials, COVID-19 delays and schedule risks will place pressure on NASA's ability to achieve this launch date.

Development cost estimates for key programs also increased. The cost of the SLS program increased by 42.5 percent and the EGS program by 32.3 percent since 2014, for a combined increase of over $3 billion, bringing the total to $11.5 billion. NASA does not plan to complete revised estimates for Orion, which are tied to the second, crewed test flight (Artemis II) before spring 2021.

NASA awarded billions of dollars in development and production contracts to support flights beyond Artemis I, but the flight schedule has changed frequently due to a lack of clear requirements and time frames for planned capability upgrades. Limited NASA oversight also places efforts to plan and execute future flights at risk of adverse outcomes, such as increased costs or delays. For example, NASA is committed to establishing cost and schedule performance baselines for these efforts, but it plans to do so too late in the acquisition process to be useful as an oversight tool. In addition, senior leaders do not receive consistent and comprehensive information at quarterly briefings on future efforts, such as a program to begin developing a more powerful upper stage for SLS. This is because current updates provided to NASA management focus primarily on the more short-term Artemis I and II flights. This approach places billions of dollars at risk of insufficient NASA oversight."

- Previous SLS/Orion posts
- Previous Artemis Posts



from NASA Watch https://ift.tt/37miJj7
via IFTTT

沒有留言:

張貼留言